Cargos de construcción de redes aereas

Precios a marzo del 2014 M.N.
 
Costo de estructuras de media tensión
Descripcion Materiales y equipo de instalacion permanentes
($)
Mano de obra
($)
Diseño del proyecto
($)
Supervision
($)
Costo total
($)
Retiro
($)
ESTRUCTURA TS3N 13 KV URBANA 5,309.34 1,969.91 112.35 74.93 7,466.52 1,452.67
ESTRUCTURA TS3N 23 KV URBANA 5,743.35 1,969.91 112.35 74.93 7,900.54 1,452.67
ESTRUCTURA TS3N 33 KV URBANA 6,051.88 1,969.91 112.35 74.93 8,209.07 1,452.67
ESTRUCTURA PS1N 13 KV URBANA 4,245.20 1,910.41 112.35 74.93 6,342.89 1,452.67
ESTRUCTURA PS1N 23 KV URBANA 4,389.87 1,910.41 112.35 74.93 6,487.56 1,452.67
ESTRUCTURA PS1N 33 KV URBANA 4,501.79 1,910.41 112.35 74.93 6,599.48 1,452.67
ESTRUCTURA TS2N 13 KV URBANA 4,736.10 1,934.54 112.35 74.93 6,857.92 1,452.67
ESTRUCTURA TS2N 23 KV URBANA 5,025.44 1,934.54 112.35 74.93 7,147.27 1,452.67
ESTRUCTURA TS2N 33 KV URBANA 5,193.47 1,934.54 112.35 74.93 7,315.29 1,452.67
ESTRUCTURA RD3N 13 KV URBANA 6,907.07 2,675.86 160.36 98.31 9,841.61 1,452.67
ESTRUCTURA RD20 13 KV URBANA 5,924.44 2,616.36 160.36 98.31 8,799.48 1,452.67
ESTRUCTURA RD20 23 KV URBANA 6,010.64 2,616.36 160.36 98.31 8,885.68 1,452.67
ESTRUCTURA RD20 33 KV URBANA 6,236.23 2,616.36 160.36 98.31 9,111.27 1,452.67
ESTRUCTURA RD20/RD2 13 KV URBANA 10,536.15 3,401.28 160.36 98.31 14,196.11 1,452.67
ESTRUCTURA RD20/RD2 23 KV URBANA 10,997.89 3,401.28 160.36 98.31 14,657.84 1,452.67
ESTRUCTURA RD20/RD2 33 KV URBANA 11,937.15 3,401.28 160.36 98.31 15,597.10 1,452.67
ESTRUCTURA TS20 13 KV RURAL 3,106.27 1,910.41 112.35 74.93 5,203.96 1,452.67
ESTRUCTURA TS20 23 KV RURAL 3,395.61 1,910.41 112.35 74.93 5,493.30 1,452.67
ESTRUCTURA TS20 33 KV RURAL 3,563.64 1,910.41 112.35 74.93 5,661.33 1,452.67
ESTRUCTURA RS20 13 KV RURAL 3,963.15 2,616.36 160.36 98.31 6,838.19 1,452.67
ESTRUCTURA RD3N 23 KV URBANA 8,809.87 2,675.86 160.36 98.31 11,744.40 1,452.67
ESTRUCTURA RS20 23 KV RURAL 4,049.35 2,616.36 160.36 98.31 6,924.38 1,452.67
ESTRUCTURA RS20 33 KV RURAL 4,434.97 2,616.36 160.36 98.31 7,310.00 1,452.67
ESTRUCTURA RD20 13 KV RURAL 4,406.50 2,616.36 160.36 98.31 7,281.54 1,452.67
ESTRUCTURA RD20 23 KV RURAL 4,596.87 2,616.36 160.36 98.31 7,471.91 1,452.67
ESTRUCTURA RD20 33 KV RURAL 4,878.31 2,616.36 160.36 98.31 7,753.35 1,452.67
ESTRUCTURA RD3N 33 KV URBANA 7,025.83 2,675.86 160.36 98.31 9,960.37 1,452.67
ESTRUCTURA TS20 13 KV RURAL (POSTE 12M) 4,464.19 1,910.41 112.35 74.93 6,561.88 1,452.67
ESTRUCTURA TS20 23 KV RURAL (POSTE 12M) 4,753.53 1,910.41 112.35 74.93 6,851.22 1,452.67
ESTRUCTURA TS20 33 KV RURAL (POSTE 12M) 4,921.56 1,910.41 112.35 74.93 7,019.25 1,452.67
ESTRUCTURA RS20 13 KV RURAL (POSTE 12M) 5,321.07 2,616.36 160.36 98.31 8,196.11 1,452.67
ESTRUCTURA RS20 23 KV RURAL (POSTE 12M) 5,407.27 2,616.36 160.36 98.31 8,282.31 1,452.67
ESTRUCTURA RS20 33 KV RURAL (POSTE 12M) 5,792.89 2,616.36 160.36 98.31 8,667.92 1,452.67
ESTRUCTURA RD20 13 KV RURAL (POSTE 12M) 5,764.42 2,616.36 160.36 98.31 8,639.46 1,452.67
ESTRUCTURA RD20 23 KV RURAL (POSTE 12M) 5,954.79 2,616.36 160.36 98.31 8,829.83 1,452.67
ESTRUCTURA RD20 33 KV RURAL (POSTE 12M) 6,236.23 2,616.36 160.36 98.31 9,111.27 1,452.67
ESTRUCTURA TS3N 13 KV RURAL (POSTE 12M) 4,983.31 1,969.91 112.35 74.93 7,140.50 1,452.67
ESTRUCTURA RS3N 13 KV URBANA 6,214.26 2,675.86 160.36 98.31 9,148.80 1,452.67
ESTRUCTURA PS3N 13 KV RURAL (POSTE 12M) 5,375.08 1,969.91 112.35 74.93 7,532.27 1,452.67
ESTRUCTURA PS3N 23 KV RURAL (POSTE 12M) 5,918.39 1,969.91 112.35 74.93 8,075.58 1,452.67
ESTRUCTURA PS3N 33 KV RURAL (POSTE 12M) 6,089.04 1,969.91 112.35 74.93 8,246.23 1,452.67
ESTRUCTURA PS1N 13 KV RURAL (POSTE 12M) 4,245.20 1,910.41 112.35 74.93 6,342.89 1,452.67
ESTRUCTURA PS1N 23 KV RURAL (POSTE 12M) 4,389.87 1,910.41 112.35 74.93 6,487.56 1,452.67
ESTRUCTURA PS1N 33 KV RURAL (POSTE 12M) 4,501.79 1,910.41 112.35 74.93 6,599.48 1,452.67
ESTRUCTURA TS2N 13 KV RURAL (POSTE 12M) 4,784.11 1,934.54 112.35 74.93 6,905.93 1,452.67
ESTRUCTURA TS2N 23 KV RURAL (POSTE 12M) 5,073.45 1,934.54 112.35 74.93 7,195.27 1,452.67
ESTRUCTURA TS2N 33 KV RURAL (POSTE 12M) 5,241.48 1,934.54 112.35 74.93 7,363.30 1,452.67
ESTRUCTURA RD3N 13 KV RURAL (POSTE 12M) 6,922.87 2,675.86 160.36 98.31 9,857.41 1,452.67
ESTRUCTURA RS3N 23 KV URBANA 7,600.72 2,675.86 160.36 98.31 10,535.26 1,452.67
ESTRUCTURA RD3N 23 KV RURAL (POSTE 12M) 8,309.33 2,675.86 160.36 98.31 11,243.86 1,452.67
ESTRUCTURA RD3N 33 KV RURAL (POSTE 12M) 7,041.63 2,675.86 160.36 98.31 9,976.16 1,452.67
ESTRUCTURA RS3N 13 KV RURAL (POSTE 12M) 6,123.38 2,675.86 160.36 98.31 9,057.91 1,452.67
ESTRUCTURA RS3N 23 KV RURAL (POSTE 12M) 7,509.84 2,675.86 160.36 98.31 10,444.37 1,452.67
ESTRUCTURA RS3N 33 KV RURAL (POSTE 12M) 6,242.14 2,675.86 160.36 98.31 9,176.67 1,452.67
ESTRUCTURA HS3G 13 KV RURAL (POSTE 12M) 15,286.29 4,531.37 219.94 149.86 20,187.47 1,452.67
ESTRUCTURA HS3G 23 KV RURAL (POSTE 12M) 16,672.75 4,531.37 219.94 149.86 21,573.93 1,452.67
ESTRUCTURA HS3G 33 KV RURAL (POSTE 12M) 15,405.05 4,531.37 219.94 149.86 20,306.23 1,452.67
ESTRUCTURA HA3G 13 KV RURAL (POSTE 12M) 24,529.91 7,355.15 345.22 196.64 32,426.93 1,452.67
ESTRUCTURA HA3G 23 KV RURAL (POSTE 12M) 27,302.83 7,355.15 345.22 196.64 35,199.85 1,452.67
ESTRUCTURA RS3N 33 KV URBANA 6,333.02 2,675.86 160.36 98.31 9,267.56 1,452.67
ESTRUCTURA HA3G 33 KV RURAL (POSTE 12M) 24,767.43 7,355.15 345.22 196.64 32,664.45 1,452.67
ESTRUCTURA RS30 13 KV RURAL (POSTE 12M) 5,739.04 2,640.49 160.36 98.31 8,638.21 1,452.67
ESTRUCTURA RS30 23 KV RURAL (POSTE 12M) 7,125.50 2,640.49 160.36 98.31 10,024.67 1,452.67
ESTRUCTURA RS30 33 KV RURAL (POSTE 12M) 5,857.80 2,640.49 160.36 98.31 8,756.97 1,452.67
ESTRUCTURA RD30 13 KV RURAL (POSTE 12M) 6,177.08 2,640.49 160.36 98.31 9,076.25 1,452.67
ESTRUCTURA RD30 23 KV RURAL (POSTE 12M) 6,306.38 2,640.49 160.36 98.31 9,205.54 1,452.67
ESTRUCTURA RD30 33 KV RURAL (POSTE 12M) 6,884.80 2,640.49 160.36 98.31 9,783.97 1,452.67
ESTRUCTURA PS30 13 KV RURAL (POSTE 12M) 5,103.17 1,934.54 112.35 74.93 7,224.99 1,452.67
ESTRUCTURA PS30 23 KV RURAL (POSTE 12M) 5,565.09 1,934.54 112.35 74.93 7,686.91 1,452.67
ESTRUCTURA PS30 33 KV RURAL (POSTE 12M) 5,817.13 1,934.54 112.35 74.93 7,938.95 1,452.67
ESTRUCTURA VS3N 13 KV URBANA 5,373.58 1,969.91 112.35 74.93 7,530.76 1,452.67
ESTRUCTURA VS3N 23 KV URBANA 5,807.59 1,969.91 112.35 74.93 7,964.78 1,452.67
ESTRUCTURA VS3N 33 KV URBANA 6,097.86 1,969.91 112.35 74.93 8,255.05 1,452.67
ESTRUCTURA RS2N 13 KV URBANA 6,201.62 2,640.49 160.36 98.31 9,100.78 1,452.67
ESTRUCTURA RS2N 23 KV URBANA 7,115.88 2,640.49 160.36 98.31 10,015.05 1,452.67
ESTRUCTURA RS2N 33 KV URBANA 6,166.88 2,640.49 160.36 98.31 9,066.05 1,452.67
ESTRUCTURA RS1N 13 KV URBANA 5,489.76 2,616.36 160.36 98.31 8,364.79 1,452.67
ESTRUCTURA RS1N 23 KV URBANA 5,636.71 2,616.36 160.36 98.31 8,511.75 1,452.67
ESTRUCTURA RS1N 33 KV URBANA 5,829.52 2,616.36 160.36 98.31 8,704.56 1,452.67
ESTRUCTURA RD1N 13 KV URBANA 8,058.22 2,616.36 160.36 98.31 10,933.26 1,452.67
ESTRUCTURA RD1N 23 KV URBANA 9,127.20 2,616.36 160.36 98.31 12,002.24 1,452.67
ESTRUCTURA RD1N 33 KV URBANA 8,366.08 2,616.36 160.36 98.31 11,241.12 1,452.67
ESTRUCTURA RD2N 13 KV URBANA 6,669.88 2,640.49 160.36 98.31 9,569.05 1,452.67
ESTRUCTURA RD2N 23 KV URBANA 7,594.19 2,640.49 160.36 98.31 10,493.36 1,452.67
ESTRUCTURA RD2N 33 KV URBANA 6,749.06 2,640.49 160.36 98.31 9,648.22 1,452.67
ESTRUCTURA RD3N/RD3 13 KV URBANA 11,337.35 3,478.62 160.36 98.31 15,074.64 1,452.67
ESTRUCTURA RD3N/RD3 23 KV URBANA 14,399.61 3,478.62 160.36 98.31 18,136.90 1,452.67
ESTRUCTURA RD3N/RD3 33 KV URBANA 12,032.24 3,478.62 112.35 98.31 15,721.51 1,452.67
ESTRUCTURA RD2N/RD2 13 KV URBANA 10,376.70 3,300.62 160.36 98.31 13,936.00 1,452.67
ESTRUCTURA RD2N/RD2 23 KV URBANA 12,514.65 3,300.62 160.36 98.31 16,073.95 1,452.67
ESTRUCTURA RD2N/RD2 33 KV URBANA 10,992.41 3,300.62 160.36 98.31 14,551.71 1,452.67
ESTRUCTURA TS3N 13 KV RURAL 3,897.65 1,969.91 112.35 74.93 6,054.84 1,452.67
ESTRUCTURA PS3N 13 KV RURAL 4,289.42 1,969.91 112.35 74.93 6,446.61 1,452.67
ESTRUCTURA PS3N 23 KV RURAL 4,751.34 1,969.91 112.35 74.93 6,908.53 1,452.67
ESTRUCTURA PS3N 33 KV RURAL 5,003.38 1,969.91 112.35 74.93 7,160.57 1,452.67
ESTRUCTURA PS1N 13 KV RURAL 3,159.54 1,910.41 112.35 74.93 5,257.23 1,452.67
ESTRUCTURA PS1N 23 KV RURAL 3,304.21 1,910.41 112.35 74.93 5,401.90 1,452.67
ESTRUCTURA PS1N 33 KV RURAL 3,416.13 1,910.41 112.35 74.93 5,513.82 1,452.67
ESTRUCTURA TS2N 23 KV RURAL 3,987.79 1,934.54 112.35 74.93 6,109.61 1,452.67
ESTRUCTURA TS2N 33 KV RURAL 4,155.82 1,934.54 112.35 74.93 6,277.64 1,452.67
ESTRUCTURA RD3N 13 KV RURAL 5,837.21 2,675.86 160.36 98.31 8,771.74 1,452.67
ESTRUCTURA RD3N 23 KV RURAL 7,223.67 2,675.86 160.36 98.31 10,158.20 1,452.67
ESTRUCTURA RD3N 33 KV RURAL 5,955.97 2,675.86 160.36 98.31 8,890.50 1,452.67
ESTRUCTURA RS3N 13 KV RURAL 5,037.72 2,675.86 160.36 98.31 7,972.25 1,452.67
ESTRUCTURA RS3N 23 KV RURAL 6,424.18 2,675.86 160.36 98.31 9,358.71 1,452.67
ESTRUCTURA RS3N 33 KV RURAL 5,156.48 2,675.86 160.36 98.31 8,091.01 1,452.67
ESTRUCTURA VS30 13 KV URBANA CONCRETO 5,187.91 1,934.54 112.35 74.93 7,309.73 1,452.67
ESTRUCTURA VS30 23 KV URBANA CONCRETO 5,621.92 1,934.54 112.35 74.93 7,743.74 1,452.67
ESTRUCTURA VS30 33 KV URBANA CONCRETO 5,873.96 1,934.54 112.35 74.93 7,995.78 1,452.67
ESTRUCTURA RS30 13 KV URBANA 5,739.04 2,640.49 160.36 98.31 8,638.21 1,452.67
ESTRUCTURA RS30 23 KV URBANA 7,125.50 2,640.49 160.36 98.31 10,024.67 1,452.67
ESTRUCTURA RS30 33 KV URBANA 5,857.80 2,640.49 160.36 98.31 8,756.97 1,452.67
ESTRUCTURA RD30/RD3 13 KV URBANA 9,863.01 3,432.64 160.36 98.31 13,554.33 1,452.67
ESTRUCTURA RD30/RD3 23 KV URBANA 12,925.27 3,432.64 160.36 98.31 16,616.60 1,452.67
ESTRUCTURA RD30/RD3 33 KV URBANA 11,605.85 3,432.64 160.36 98.31 15,297.17 1,452.67
ESTRUCTURA TS20 13 KV URBANA 4,512.20 1,910.41 112.35 74.93 6,609.89 1,452.67
ESTRUCTURA TS20 23 KV URBANA 4,801.54 1,910.41 112.35 74.93 6,899.23 1,452.67
ESTRUCTURA TS20 33 KV URBANA 4,980.70 1,910.41 112.35 74.93 7,078.39 1,452.67
ESTRUCTURA RS20 13 KV URBANA 5,321.07 2,616.36 160.36 98.31 8,196.11 1,452.67
ESTRUCTURA RS20 23 KV URBANA 5,407.27 2,616.36 160.36 98.31 8,282.31 1,452.67
ESTRUCTURA RS20 33 KV URBANA 5,792.89 2,616.36 160.36 98.31 8,667.92 1,452.67
ESTRUCTURA TS3N 13 KV URBANA MADERA 5,255.38 1,969.91 112.35 74.93 7,412.56 1,452.67
ESTRUCTURA TS3N 23 KV URBANA MADERA 5,806.40 1,969.91 112.35 74.93 7,963.59 1,452.67
ESTRUCTURA TS3N 33 KV URBANA MADERA 6,930.33 1,969.91 112.35 74.93 9,087.51 1,452.67
ESTRUCTURA PS1N 13 KV URBANA MADERA 4,074.12 1,910.41 112.35 74.93 6,171.81 1,452.67
ESTRUCTURA PS1N 23 KV URBANA MADERA 4,285.70 1,910.41 112.35 74.93 6,383.39 1,452.67
ESTRUCTURA PS1N 33 KV URBANA MADERA 4,651.85 1,910.41 112.35 74.93 6,749.55 1,452.67
ESTRUCTURA TS2N 13 KV URBANA MADERA 4,983.37 1,934.54 112.35 74.93 7,105.19 1,452.67
ESTRUCTURA TS2N 23 KV URBANA MADERA 5,350.72 1,934.54 112.35 74.93 7,472.54 1,452.67
ESTRUCTURA TS2N 33 KV URBANA MADERA 6,108.49 1,934.54 112.35 74.93 8,230.31 1,452.67
ESTRUCTURA RD3N 13 KV URBANA MADERA 7,471.49 2,675.86 160.36 98.31 10,406.02 1,452.67
ESTRUCTURA TS3N P/477 33 KV RURAL 6,930.33 1,969.91 112.35 74.93 9,087.51 1,452.67
ESTRUCTURA RT3N/RT3 13 KV RURAL 13,112.75 3,478.62 160.36 98.31 16,850.05 1,452.67
ESTRUCTURA RT3N/RT3 23 KV RURAL 11,910.25 3,478.62 160.36 98.31 15,647.54 1,452.67
ESTRUCTURA RT3N/RT3 33 KV RURAL 12,985.03 3,478.62 160.36 98.31 16,722.33 1,452.67
ESTRUCTURA RD3N 23 KV URBANA MADERA 6,778.40 2,675.86 160.36 98.31 9,712.93 1,452.67
ESTRUCTURA RD3N 33 KV URBANA MADERA 7,167.69 2,675.86 160.36 98.31 10,102.23 1,452.67
ESTRUCTURA RS3N 13 KV URBANA MADERA 6,689.47 2,675.86 160.36 98.31 9,624.01 1,452.67
ESTRUCTURA RS3N 23 KV URBANA MADERA 5,963.55 2,675.86 160.36 98.31 8,898.09 1,452.67
ESTRUCTURA RS3N 33 KV URBANA MADERA 6,317.87 2,675.86 160.36 98.31 9,252.40 1,452.67
ESTRUCTURA VS30 13 KV URBANA MADERA 5,219.20 1,934.54 112.35 74.93 7,341.02 1,452.67
ESTRUCTURA VS30 23 KV URBANA MADERA 5,770.22 1,934.54 112.35 74.93 7,892.04 1,452.67
ESTRUCTURA VS30 33 KV URBANA MADERA 6,886.18 1,934.54 112.35 74.93 9,008.00 1,452.67
ESTRUCTURA TS3N 13 KV RURAL MADERA 5,333.50 1,969.91 112.35 74.93 7,490.69 1,452.67
ESTRUCTURA PS3N 13 KV RURAL MADERA 5,448.24 1,969.91 112.35 74.93 7,605.43 1,452.67
ESTRUCTURA PS3N 23 KV RURAL MADERA 5,999.26 1,969.91 112.35 74.93 8,156.45 1,452.67
ESTRUCTURA PS3N 33 KV RURAL MADERA 7,104.36 1,969.91 112.35 74.93 9,261.55 1,452.67
ESTRUCTURA PS1N 13 KV RURAL MADERA 4,074.12 1,910.41 112.35 74.93 6,171.81 1,452.67
ESTRUCTURA PS1N 23 KV RURAL MADERA 4,285.70 1,910.41 112.35 74.93 6,383.39 1,452.67
ESTRUCTURA PS1N 33 KV RURAL MADERA 4,651.85 1,910.41 112.35 74.93 6,749.55 1,452.67
ESTRUCTURA TS2N 13 KV RURAL MADERA 4,983.37 1,934.54 112.35 74.93 7,105.19 1,452.67
ESTRUCTURA TS2N 23 KV RURAL MADERA 5,350.72 1,934.54 112.35 74.93 7,472.54 1,452.67
ESTRUCTURA TS2N 33 KV RURAL MADERA 6,108.49 1,934.54 112.35 74.93 8,230.31 1,452.67
ESTRUCTURA RD3N 13 KV RURAL MADERA 7,471.49 2,675.86 160.36 98.31 10,406.02 1,452.67
ESTRUCTURA RD3N 23 KV RURAL MADERA 6,778.40 2,675.86 160.36 98.31 9,712.93 1,452.67
ESTRUCTURA RD3N 33 KV RURAL MADERA 7,167.69 2,675.86 160.36 98.31 10,102.23 1,452.67
ESTRUCTURA RS3N 23 KV RURAL MADERA 5,963.55 2,675.86 160.36 98.31 8,898.09 1,452.67
ESTRUCTURA RS3N 33 KV RURAL MADERA 6,317.87 2,675.86 160.36 98.31 9,252.40 1,452.67
ESTRUCTURA HS3G 13 KV RURAL MADERA 16,990.24 4,531.37 219.94 74.93 21,816.49 1,452.67
ESTRUCTURA HS3G 23 KV RURAL MADERA 16,297.15 4,531.37 219.94 74.93 21,123.40 1,452.67
ESTRUCTURA HS3G 33 KV RURAL MADERA 16,651.47 4,531.37 219.94 74.93 21,477.72 1,452.67
ESTRUCTURA HA3G 13 KV RURAL MADERA 25,099.12 7,355.15 345.22 98.31 32,897.81 1,452.67
ESTRUCTURA HA3G 23 KV RURAL MADERA 23,712.94 7,355.15 345.22 98.31 31,511.63 1,452.67
ESTRUCTURA HA3G 33 KV RURAL MADERA 24,421.57 7,355.15 345.22 98.31 32,220.26 1,452.67
ESTRUCTURA TS3N 23 KV RURAL MADERA 5,839.23 1,969.91 112.35 74.93 7,996.42 1,452.67
ESTRUCTURA TS3N 33 KV RURAL MADERA 6,922.14 1,969.91 112.35 74.93 9,079.32 1,452.67
ESTRUCTURA RD2N 13 KV URBANA MADERA 7,028.17 2,640.49 160.36 98.31 9,927.33 1,452.67
ESTRUCTURA RD2N 23 KV URBANA MADERA 6,566.11 2,640.49 160.36 98.31 9,465.27 1,452.67
ESTRUCTURA RD2N 33 KV URBANA MADERA 6,802.32 2,640.49 160.36 98.31 9,701.48 1,452.67
ESTRUCTURA RS2N 13 KV URBANA MADERA 6,252.38 2,640.49 160.36 98.31 9,151.55 1,452.67
ESTRUCTURA RS2N 23 KV URBANA MADERA 5,790.32 2,640.49 160.36 98.31 8,689.49 1,452.67
ESTRUCTURA RS2N 33 KV URBANA MADERA 6,026.53 2,640.49 160.36 98.31 8,925.70 1,452.67
ESTRUCTURA RP1N 13 KV URBANA MADERA 4,930.44 2,640.49 160.36 98.31 7,829.61 1,452.67
ESTRUCTURA RP1N 23 KV URBANA MADERA 4,699.41 2,616.36 160.36 98.31 7,574.45 1,452.67
ESTRUCTURA RP1N 33 KV URBANA MADERA 4,817.51 2,616.36 160.36 98.31 7,692.55 1,452.67
ESTRUCTURA RD2N 13 KV RURAL MADERA 7,028.17 2,640.49 160.36 98.31 9,927.33 1,452.67
ESTRUCTURA RD2N 23 KV RURAL MADERA 6,566.11 2,640.49 160.36 98.31 9,465.27 1,452.67
ESTRUCTURA RD2N 33 KV RURAL MADERA 6,802.32 2,640.49 160.36 98.31 9,701.48 1,452.67
ESTRUCTURA RS2N 13 KV RURAL MADERA 6,252.38 2,616.36 160.36 98.31 9,127.42 1,452.67
ESTRUCTURA RS2N 23 KV RURAL MADERA 5,790.32 2,616.36 320.72 98.31 8,825.71 1,452.67
ESTRUCTURA RS2N 33 KV RURAL MADERA 6,026.53 2,616.36 160.36 98.31 8,901.57 1,452.67
ESTRUCTURA RP1N 13 KV RURAL MADERA 4,930.44 2,616.36 160.36 98.31 7,805.48 1,452.67
ESTRUCTURA RP1N 23 KV RURAL MADERA 4,699.41 2,616.36 160.36 98.31 7,574.45 1,452.67
ESTRUCTURA RP1N 33 KV RURAL MADERA 4,817.51 2,616.36 160.36 98.31 7,692.55 1,452.67
ESTRUCTURA RD3N/RD3 13 KV URBANA 12,157.70 3,478.62 160.36 98.31 15,895.00 1,452.67
ESTRUCTURA RD3N/RD3 23 KV URBANA 11,138.87 3,478.62 160.36 98.31 14,876.16 1,452.67
ESTRUCTURA RD3N/RD3 33 KV URBANA 13,198.17 3,478.62 160.36 98.31 16,935.46 1,452.67
ESTRUCTURA RD2N/RD2 13 KV URBANA 11,275.14 3,300.62 160.36 98.31 14,834.44 1,452.67
ESTRUCTURA RD2N/RD2 23 KV URBANA 10,718.37 3,300.62 160.36 98.31 14,277.67 1,452.67
ESTRUCTURA RD2N/RD2 33 KV URBANA 11,923.10 3,300.62 160.36 98.31 15,482.40 1,452.67
ESTRUCTURA RP1N/RP1 13 KV URBANA 6,478.55 2,616.36 160.36 98.31 9,353.58 1,452.67
ESTRUCTURA RP1N/RP1 23 KV URBANA 6,016.49 2,616.36 160.36 98.31 8,891.52 1,452.67
ESTRUCTURA RP1N/RP1 33 KV URBANA 6,252.70 2,616.36 160.36 98.31 9,127.73 1,452.67
ESTRUCTURA RT3N 13 KV URBANA 9,046.53 2,675.86 160.36 98.31 11,981.07 1,452.67
ESTRUCTURA RT3N 23 KV URBANA 8,353.44 2,675.86 160.36 98.31 11,287.98 1,452.67
ESTRUCTURA RT3N 33 KV URBANA 8,707.76 2,675.86 160.36 98.31 11,642.29 1,452.67
ESTRUCTURA RT3N/RT3 13 KV URBANA 13,112.75 3,478.62 160.36 98.31 16,850.05 1,452.67
ESTRUCTURA RT3N/RT3 23 KV URBANA 11,910.25 3,478.62 160.36 98.31 15,647.54 1,452.67
ESTRUCTURA RT3N/RT3 33 KV URBANA 12,985.03 3,478.62 160.36 98.31 16,722.33 1,452.67
ESTRUCTURA TS3N P/477 13 KV URBANA 5,280.83 1,969.91 112.35 74.93 7,438.02 1,452.67
ESTRUCTURA TS3N P/477 23 KV URBANA 5,831.85 1,969.91 112.35 74.93 7,989.04 1,452.67
ESTRUCTURA TS3N P/477 33 KV URBANA 6,930.33 1,969.91 112.35 74.93 9,087.51 1,452.67
ESTRUCTURA TS3N P/477 13 KV RURAL 5,280.83 1,969.91 112.35 74.93 7,438.02 1,452.67
ESTRUCTURA TS3N P/477 23 KV RURAL 5,831.85 1,969.91 112.35 74.93 7,989.04 1,452.67
ESTRUCTURA TS30 23 KV URBANA 13,751.85 1,934.54 112.35 74.93 15,873.67 1,452.67
ESTRUCTURA TS30 33 KV URBANA 14,003.89 1,934.54 112.35 74.93 16,125.71 1,452.67
ESTRUCTURA RD3N 13 KV URBANA 15,710.91 2,675.86 160.36 98.31 18,645.44 1,452.67
ESTRUCTURA RD3N 23 KV URBANA 18,483.83 2,675.86 160.36 98.31 21,418.36 1,452.67
ESTRUCTURA RD3N 33 KV URBANA 15,948.43 2,675.86 160.36 98.31 18,882.96 1,452.67
ESTRUCTURA RS3N 13 KV URBANA 14,568.59 2,675.86 160.36 98.31 17,503.13 1,452.67
ESTRUCTURA RS3N 23 KV URBANA 15,955.05 2,675.86 160.36 98.31 18,889.59 1,452.67
ESTRUCTURA RS3N 33 KV URBANA 14,687.35 2,675.86 160.36 98.31 17,621.89 1,452.67
ESTRUCTURA VS30 13 KV URBANA ACERO 13,631.34 1,934.54 112.35 74.93 15,753.16 1,452.67
ESTRUCTURA VS30 23 KV URBANA ACERO 14,065.35 1,934.54 112.35 74.93 16,187.17 1,452.67
ESTRUCTURA VS30 33 KV URBANA ACERO 14,317.39 1,934.54 112.35 74.93 16,439.21 1,452.67

icoNotasNota:
Estos costos no incluyen IVA